Newbury Central, Ilford

Client:Bellway Homes
Type:New build residential
Value:£990,000
Duration:Mar 2004 - Jun 2005
Architect:Bellway Homes
M&E Consultant:Design Brook
PQS:Bellway Homes
Contract:JCT' 80
Newbury Central

This project was secured through the competitive tender route.

The works involved the installation of mechanical and electrical services for 154 medium quality flats arranged in 4 separate blocks. The central electrical, water and drainage services were routed through the underground car park area to the blocks in vertical risers.

An in-depth detailed design review process was carried out to resolve quality issues in the flats.

The project was completed in 3 phases. Tenants took possession of their dwellings prior to completion of all blocks. This necessitated setting to work and maintaining the operation of partially completed central systems - mains distribution, water supplies, car park ventilation and drainage.

Recent News

Phase II of the Scottish & Newcastle upgrade works were secured in early May 2010

More....

49 Grosvenor Street, Mayfair commenced on site in March 2010

More....

Client Testimonial

Trinity have been used by Longcross Construction over the last 2 years on a number of commercial and university projects.

We have found them to be an excellent, pro-active M&E sub-contractor. They have not let us down and have shown good technical understanding on some difficult...

Longcross Group Ltd

View All Testimonials

Industry Membership Links